It seems that we must cut all of the major expenditures of our
federal government if we are to balance the budget of our great nation,
as our national debt is going to an non-viable place. This means we will
have to cut Social Security, Medicare, and yes, some of our military as
well. Some in Washington DC have said there can't be any sacred cows.
Of course we know that's not how Washington DC works. Okay so let's talk
about places we can make cuts.
One place the Pentagon has
identified is in the government contracting of large weapons systems.
Some believe that the contractor should agree on a fixed cost, and not
be allowed to add additional expenses, or cost overruns on their part.
Well, it's not usually the contractor that causes the increase, it is
often that the military changes their needs, or the politicians
themselves choose a different path forward based on current world events
and politics.
Not long ago, I read a research paper titled;
"Fixed-Price Development: Contracts: A Historical Perspective," by
William Lucyshyn from the Center of Public Policy and Private Enterprise
School of Public Policy at the University of Maryland which was
published on May 16, 2012, and the paper noted amongst other things
that:
"A 2006 RAND report found that the average adjusted total
cost growth for a completed program was 46 percent (RAND TR-343) and the
roughly 100 projects under development during fiscal year 2007
experienced average cost growth of 26 percent and average schedule delay
of 21 months over initial estimates (GAO-08-1159T) and that the GAO
also estimated that these programs will cost $295B more than originally
projected."
Things that I believe are some of the biggest causes
in all of this I've listed below. And as someone that runs a think tank
we talk about this a lot because it is not just military contracting
where this occurs, it happens any time you are developing new
prototypes, or innovating in just about any industry or subsector. The
issues we most encounter happen to be;
Rush orders
Feature Creep
Change Orders Due to New Needs
Availability of supplies or raw material increases
Feature Creep
Change Orders Due to New Needs
Availability of supplies or raw material increases
The
authors of the research paper above that I mentioned suggest in
studying 4 major weapons system case studies; The C-5 Galaxy, the Boeing
Aerial Tanker, The A-12, and the F-111 that amongst other things the
main challenges in cost overruns and project delays were;
Design stability
Production maturity
Changing requirements
Technological unknowns
Inaccurate cost estimates
Production maturity
Changing requirements
Technological unknowns
Inaccurate cost estimates
Thus,
suggesting that; "A "Fixed-Price" contract is often anything but
fixed-price." Further, although these "contracts appear to be less risky
than cost-reimbursement contracts, the results prove that not to be the
case, and large, complex projects will generally experience schedule
slips, technical changes, and cost growth, as the programs evolve," and
so in conclusion the author's point out that such contracts "do not
eliminate these challenges, and may produce perverse incentives that
make the problems worse."
What I'm saying is it may not be
something that is that easy to fix. Often these large weapons contracts
take years to complete, and sometimes the game changes midstream.
Consider if you will a weapons contract which was awarded in the year
2000, before 9/11. Along came 9/11, and a new enemy emerged, and
therefore those other weapons systems were not needed for their typical
purposes, so therefore many change orders needed to be made, so they
could be utilized as assets fighting the war on terror instead. Are you
beginning to see my point here?
No comments:
Post a Comment